Bought-in Part Planning
The Challenge
Problem
• Average stock coverage of 67 days, with average supplier Lead Time of 31 days
• £18.1m worth of inventory held in stock due to inconsistent deliveries by the supplier
• 4000 pallets stored in the warehouse
Root Causes
• Lack of frequent KPI tracking: stock value, stock coverage or supplier Lead Time
• Component ordering based on forecasts with low accuracy
• No repercussions for suppliers who fail to comply with service level agreements
The Solution
• Implementation of Periodic ABC Classification (frequency and volume) to identify Material Requirement Planning and Reorder Point articles
• Reorder Point Pilot Tool in Excel to validate the concept
• Renegotiation of supplier contracts: Lead Times, frequency of delivery, minimum order quantity, consignment and packaging
• Pull Planning Manual and Standardisation of planning processes
• Standard Reports to communicate with suppliers
The Results
The organisation was able to free more than £2.3 million in Cashflow.
#assembly manufacturing #sourcing